Airfield Lighting Rehabilitation- Rockcliffe Airport

In the fall of 2021, HM Aero and Gibbings Consulting were retained by Ingenium to identify requirements and provide Class ‘C’ cost estimates to replace the entire lighting system associated with Runway 09-27 at Rockcliffe Airport.  The existing aerodrome lighting system dated back to the 1970s and only one-third of the runway was equipped with edge lighting.

HM Aero worked closely with Ingenium to prepare a Design Basis Memorandum that identified specific lighting requirements including edge lighting, threshold/end lighting, wing bars, taxiway edge lights, PAPIs and illuminated signage. The project team also completed an obstacle analysis to confirm placement of thresholds for Runways 09 and 27 and to identify obstacles for removal as per the requirements of TP312 5th Edition.  The construction value of the assignment was estimated at $1 Million.

Following acceptance of the Design Basis Memorandum, Ingenium commissioned HM Aero and Gibbings Consulting in early 2022 to prepare the detailed design and tender documents to solicit contractors to complete the work in the fall of the same year. The detailed design exercise included preparation of 60%, 95% and Issue for Tender design submission, specifications, and tender packages.  HM Aero also defined Safety Management System, NOTAM requirements, safety protocols and procedures for construction, and completed a NAV CANADA Land Use Submission as part of the assignment.

Advance tenders were issued for airfield lighting equipment to ensure availability for construction in 2022 and HM Aero assisted Ingenium by identifying equipment requirements and suppliers and preparing tender documents.  HM Aero provided Ingenium with site supervision and inspection services and construction was completed in early spring of 2023.  The assignment was delivered on schedule, and within budget.

Client: Ingenium (Canadian Aviation and Space Museum)

Services:

  • Airport Planning

  • Airfield Lighting Engineering Design

  • Tender and Specification Preparation

  • Cost Estimating

  • Construction Staging

  • Plan of Construction Operations and Staging

  • Resident Site Supervision

  • Owner’s Representative

Project Completed: 2021-2023

Previous
Previous

Taxiway Pavement and Lighting Rehabilitation - Sarnia Airport

Next
Next

Airfield Pavement Rehabilitation - Golden Municipal Airport